![]() |
Forming the transfer girders. |
![]() |
More foam negative blocks affixed to plywood formwork. |
![]() |
I believe these stones belong atop the temple spires. The spheres, which look small from the ground, are enormous up-close - perhaps 4 feet in diameter. |
![]() |
Each stone is tagged with a description and QR code. This tag says "Tower Stones > East Center Tower > Upper Spire > ECT-3. |
![]() |
Finished spires appear near the end of November, 2023. |
![]() |
East temple wall transfer girder formwork. At the center of the photo, we see rebar connecting the interior and exterior transfer girders. |
![]() |
Iron fencing has replaced portions of the solid wall surrounding Temple Square. |
![]() |
The west patron entrance pavilion taking shape. The concrete structure is full of arches and steel embed plates. |
![]() |
Extensive reinforcing in the transfer girder running north of the temple's east wall. The rebar lengths vary with the irregular foundation stones. |
![]() |
The foundation of the Assembly Hall has been exposed and rebar placed. Shotcrete will be applied to fortify the foundation stones. |
![]() |
Footings move southward between the west temple wall and the tabernacle. |
![]() |
Steel is going up on the west patron entrance pavilion. |
![]() |
Concrete walls rise to the east of the temple. These areas will contain space for temple workers. |
![]() |
Framing mockup for the glass ceiling in the entry hallway. See the rendering produced by the church below. |
![]() |
![]() |
Formwork for the east transfer girder is removed. Here you can see some of the negative foam blocks before they are removed. |
![]() |
Looking northwest at the north end of the east transfer girder. |
![]() |
Sensors have been placed at the center of each girder at the base isolator level. I assume care is taken to monitor all movement of the temple and the new foundation while installation progresses. |
![]() |
Cable placement and tensioning is nearly complete in the west transfer girder. At left, the concrete structure for the North temple wing has reached ground level. |
![]() |
The gap in this wall will be the main entry into the historic temple from the North addition. |
![]() |
Cable placement progressing on the east transfer girder. |
![]() |
A new hole in the historic temple wall is shown at center. |
![]() |
Work on the grounds between the assembly hall and tabernacle is moving along. |
![]() |
After cables are tensioned, the excess is cut off and a cap is placed over the ends. |
![]() |
This worker creates a shower of sparks as he cuts off cable ends. |
![]() |
Rebar is being placed for the North transfer girder. |
![]() |
Walls and columns go up for the underground area south of the temple. This will be mainly mechanical space, with a large stormwater detention chamber. |
![]() |
More work on the grounds Southwest of the temple. This small seating area will be finished with crushed rock and sand, so the slab beneath has small pipes to allow drainage through the concrete. |
![]() |
Small tubes and valves extend from the top of each cable cap. Perhaps this is where grout will be pumped into the conduits. |
No comments:
Post a Comment